image
image



Type:      Overlay
Project:  Campau Subdivision

PROJECT
Road Various
Between S of Water Street
Township Port Huron
FUNDING
Road Commission: $ 58,000
Township/County: $ 130,000
Federal: $ 0
RC Millage Funds:
(to match Federal Funds)
   

Total Project Cost:

$ 188,000
PROJECT DATES
Anticipated Bid: February 2016
Anticipated Start:  May 2016
Anticipated Completion:  June 2016
MISCELLANEOUS
Contractor Ace-Saginaw Paving 
Notes:  
Project Status:  Project Complete
   
All amounts and dates are estimates unless otherwise noted.

 