Type:      Replacement
Project:  Boardman Road Bridge

PROJECT
Road Bordman Road over Shafer Drain
Between Wahl Road and Belle River Road
Township Riley
 
Road Commission: $ 152,164
Township/County: $ 0
Federal: $ 706,115
RC Millage Funds:
(to match Federal Funds)
$ 37,164

Total Project Cost:

$ 858,279
PROJECT DATES
Anticipated Bid:  March 2016
Anticipated Start:  June 2016
Anticipated Completion:  September 2016
MISCELLANEOUS
Contractor Z Contractors 
Notes:  
Project Status:  Complete
   
All amounts and dates are estimates unless otherwise noted.

 