image
image



Type:      Reconstruction
Project:  Parker Road

PROJECT
Road Parker Road
Between Keewahdin to M-136
Township Fort Gratiot
FUNDING
Road Commission: $ 68,500
Township/County: $ 52,000
Federal: $ 0
RC Millage Funds:
(to match Federal Funds)

Total Project Cost:

$ 118,500
PROJECT DATES
Anticipated Bid:  April 2016
Anticipated Start: October 2016
Anticipated Completion: October 2016
MISCELLANEOUS
Contractor Ace-Saginaw paving
Notes:  
Project Status:  Starting week of October 10th
   
All amounts and dates are estimates unless otherwise noted.

 

image

 

image

image